Phase 10 handoff for PRODUCT-REVIEW-01

11 November 2026. Prepared; entry decision pending. Read ACCEPTANCE_PROPOSAL.md and record the Phase 10 milestone decision before treating this as an accepted predecessor.

Baselines

The frozen cleanup branch is feature/phase10-cleanup in the p10-assessment worktree. Accepted predecessor 5cb903b989742b7a96cb22ddf4c0e24993b18980 contains frozen source ba04d817fed26d659bfa2a56b089d6cac851dc34. CLEAN-20 removed only unused App.css. Current P10 source, evidence and group reconciliation are recorded in P10-00–05 and PRESERVATION_DISPOSITION.json.

The separately developed A3 successor is codex/a3-ui-10 in direct-roadmap-integration. Use docs/direct-roadmap/LATEST_CHECKPOINT.md for its exact published ref. Its scoped implementation receipts and final Gate F are separate. Select the latest accepted application integration as the review baseline, and record its source identity before findings. The frozen cleanup approval alone does not accept a later A3 successor.

Accepted evidence to carry with its original scope

  • CLEAN-20 candidate proof, rollback and five fresh browser cases are in P10-01.
  • Canonical Career Profile, historical/imported CVs, letters, frozen packages, renderer compatibility, revision ownership and RD21 are retained in P10-02.
  • Backend/configuration/dependency retention and separate SQLite retirement gates are in P10-03.
  • Local full regression comprises 1,448 backend and 1,031 frontend cases. Native receipts, raw hashes, independent integrity checks and historical environment/fixture binding are in P10-05. Earlier selected totals overlap.
  • The 57 preservation groups retain 56 PARTIAL and one DEFERRED, with all source criteria and 34 routes preserved. Product review must inspect their remaining user-value and qualification gaps without deleting partial functionality.
  • Human/device, providers/models, advisory/security, hosted, recovery and production evidence keeps the limits in ACCEPTANCE_PROPOSAL.md. Production remains NO-GO.

Product review entry and delivery

Read complete Prompt 6 — PRODUCT-REVIEW-01.txt and its required sources. Its observed SHA-256 is 544d11a2d1e9a913397766c7e475f63338f0b735d2bb26dcabdedb6fe9e25a58. Create or reconcile planning/product-review-01 from the selected accepted development baseline. Preserve existing planning work.

Perform and record the independent actual-application/journey audit before evaluating predefined initiatives. Then produce the ranked Markdown/JSON/schema backlog, priorities, dependencies and delivery specifications required by Prompt 6. Reconcile them with the continuing direct-roadmap TODO and existing authoritative documents. Keep foundation/security/reliability work distinct from speculative commercial scoring. Product review's own deliverables are research/planning; implementation authority belongs to the applicable approved workstream.

The deferred CV-import engine overhaul and personal portfolio remain outside the task. Additional deletion, Global Jobs entry/provider rights, additional-locale publication, homepage design, protected security/operational decisions and final release retain their gates. No main merge or production deployment is authorised.