docs(phase10): record blocked checkpoint publication

This commit is contained in:
cesnimda
2026-11-02 01:02:03 +01:00
parent 7ba1367fd2
commit 8cdff28f07
3 changed files with 10 additions and 4 deletions
+3 -2
View File
@@ -1,6 +1,6 @@
# P10-00 — Direct assessment and deletion eligibility
2 November 2026, Europe/Paris. **Assessment complete; P10-01 awaits candidate-specific owner approval.** No application/test/dependency/schema change or deletion was performed. One narrowly bounded frontend stylesheet is nominated below; the other assessed areas remain retained. Phase 10 completion and post-redesign product-review acceptance are not established. Production remains NO-GO.
2 November 2026, Europe/Paris. **Assessment content complete locally; checkpoint publication BLOCKED; P10-01 awaits candidate-specific owner approval and publication.** No application/test/dependency/schema change or deletion was performed. One narrowly bounded frontend stylesheet is nominated below; the other assessed areas remain retained. Phase 10 completion and post-redesign product-review acceptance are not established. Production remains NO-GO.
## Authority, baseline and draft review
@@ -109,8 +109,9 @@ Retained independent debt: physical device/AT/contrast/proficient EN-NB/printing
| Decision | Current result |
| --- | --- |
| P10-00 direct assessment | **COMPLETE** within the authorised documentation/inspection scope |
| P10-00 checkpoint publication | **BLOCKED**: local `7ba1367fd2e84375b3065eeedf9176a34996f77b` push rejected by Gitea's crashing pre-receive hook; no Phase 10 remote ref on independent readback |
| CLEAN-20 static deletion eligibility | **NOMINATED**, with exact implementation verification and owner gate above |
| P10-01 implementation | **BLOCKED pending explicit candidate-specific approval in this chat** |
| P10-01 implementation | **BLOCKED pending explicit candidate-specific approval in this chat and required checkpoint publication** |
| Phase 10 complete acceptance | **NO-GO / NOT YET ESTABLISHED**; P10-01–05 not complete |
| Redesign development completion | Existing **CONDITIONAL GO** remains scoped; final cleanup acceptance not established |
| Post-Phase-10 PRODUCT-REVIEW-01 readiness | **NO-GO** until Phase 10 is accepted and applicable entry conditions are satisfied |