# Partial I18N-00 research handoff
|
|
|
|
Branch `feature/i18n-00-audit`, based on accepted conditional handoff `5cb903b989742b7a96cb22ddf4c0e24993b18980`. Only `docs/i18n/00/` changed. This checkpoint preserves research; I18N-00 acceptance remains IN_PROGRESS and I18N-01 implementation remains BLOCKED.
|
|
|
|
Completed: source-owner audit draft; ordered implementation contracts; source-bound English catalogue/static callers; initial 59-territory CLDR matrix; 60 planned locale candidates and schema; planning checks documented in BASELINE_TESTS.md. No locale translated, reviewed or released here.
|
|
|
|
Next authorised work, without implementation approval:
|
|
|
|
1. Resolve 188 dynamic/unknown calls, direct translation object access and wrappers. Review the 853 entries without static callers without treating them as unused.
|
|
2. Inventory hardcoded frontend/ARIA/empty/error/export text and backend/Python/email/queue strings. Assign real namespace, translator context, parameter sensitivity and owning component rather than inferring from keys.
|
|
3. Complete national/regional official-record checks beyond the initial Norway/Switzerland/Serbia checks. Expand territory/minority coverage where the current research envelope omits required contexts.
|
|
4. Evaluate actual installed/locked library compatibility and Montenegrin canonicalisation before choosing a runtime migration. Do not install packages now.
|
|
5. Obtain reviewer/market priorities when a concrete rollout proposal is ready. Keep human/native approval separate from planning completeness.
|
|
|
|
The delegated researcher was interrupted by a service usage limit; the parent continued, corrected references to nonexistent deliverables and produced the actual inventory/catalogue/matrix. No agent is working in the background. Full stage completion must not be inferred from the presence of the expected filenames.
|
|
|
|
Continuation: CONTEXT_TRIAGE.md records all 188 dynamic calls, 108 finite-branch resolutions (240 existing-key references), four direct catalogue reads and 26 source-context-reviewed JSX/accessibility literal candidates. Seven concrete planning findings I00-13 through I00-19 added. Remaining dynamic call queue is 80; prior 188 count is the original inventory total, not the remaining queue. No application changes.
|
|
|
|
Product tests NOT RUN; source equality and planning checks PASSED within their documented limits. Preserve existing PDF evidence. No application models, production services, orchestrator configuration or signing/approval material accessed.
|